Development Update May 2024
We remain scheduled for Phase 1 & 2 to begin from Monday 3rd June following the clubs’ owner’s instruction to proceed – this is fantastic for the club and marks the beginning of the exciting improvements ahead for Sand Martins.
Kingerlee will complete works as planned, and as detailed in the March update; to familiarise yourself with the project plan please Click Here
Click here to view our site plan showing the areas that will be under construction during Phase 1 & 2.
A high-level overview of milestones and project timescales the club and Kingerlee are working to are as follows;
- June – Site set up (Site office and Plant delivery).
- Mid-June – New Greenkeepers site clearance & Commencement (LHS 2nd Hole)
- Mid-June to August – Temporary car park construction
- August to January 2025 – Main car park works.
- September to March 2025 – New road works into car parks.
- TBC – substation works.
- April 2025 – Completion of all areas (Phase 1 & 2)
Kind regards
Matthew Short
General Manager